NCTI Construction Coordinator III Practice Test

Question: 1 / 400

What is an example of a performance metric in construction project management?

Cost variance

Schedule variance

In the context of construction project management, identifying an example of a performance metric involves recognizing a measure that quantifies the progress of a project against predefined criteria. Schedule variance specifically measures the difference between the work actually performed and the work planned or scheduled for a particular point in time. This metric is crucial because it helps project managers assess whether the project is ahead of, on schedule, or behind schedule.

By analyzing schedule variance, construction managers can make informed decisions about resource allocation, adjust timelines, and implement corrective actions when necessary to keep the project on track. This focus on time management is essential in ensuring that projects are delivered efficiently and within the timelines set at the project's outset.

While cost variance, quality metrics, and resource allocation are all important components of project management, schedule variance specifically addresses the critical timing aspect of project performance, making it a fundamental performance metric in this field.

Get further explanation with Examzify DeepDiveBeta

Quality metrics

Resource allocation

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy