What is the first order of business for the fiber-optic field restoration coordinator (FRC)?

Study for the NCTI Construction Coordinator III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The first order of business for the fiber-optic field restoration coordinator (FRC) is conducting a site visit to verify the extent of the damage. This step is crucial because it allows the FRC to assess the situation firsthand, which is vital for determining the specific requirements for restoration, evaluating any potential hazards, and understanding the overall impact on the fiber-optic network.

By visiting the site, the coordinator can identify not only the visible damage but also any underlying issues that may not be immediately apparent without a thorough examination. This direct assessment enables the FRC to develop a comprehensive restoration plan that addresses all aspects of the damage and prepares for subsequent steps, such as planning for repairs, managing resources, and coordinating with other teams or contractors.

The other options, although important in the overall process, come after the initial site verification. For instance, budget approvals and safety protocol documentation are essential but depend on the results of the site assessment. Similarly, alerting citizens may be necessary later in the process once the FRC has a clearer understanding of the timeline and impact of the repairs.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy