Which of the following is a potential consequence of labor disputes in construction?

Study for the NCTI Construction Coordinator III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Labor disputes in construction often lead to significant delays in project timelines. When disputes arise, whether due to disagreements over wages, working conditions, or other employment terms, construction work can come to a halt. This stoppage can be highly disruptive, leading to a cascade of scheduling conflicts that affect not just the immediate tasks, but also the overall project plan.

The resolution of labor disputes may require negotiations, mediation, or even legal interventions, all of which take time. As a result, project completion dates can be pushed back, leading to delays that can impact budgets, resource allocations, and client satisfaction. Understanding this consequence highlights the importance of effective communication and dispute resolution strategies in construction management to mitigate such risks and maintain project schedules.

While the other options suggest positive outcomes, they do not align with the reality of labor disputes. For instance, increased efficiency and reduced costs are generally outcomes of a well-functioning workforce rather than the result of conflicts. Similarly, employee morale is likely to decline during disputes rather than improve, as workers may feel undervalued or stressed during such periods.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy